Nanning metro line 2 east extension project of the entrance line shield section through
Recently, it was learned that after more than 400 days and nights of hard work, the east extension of metro line 2 has been completed, and the east extension of metro line 2 has been officially connected with the xincun parking lot, taking a solid step towards the completion of the east extension.
The east extension of metro line 2 has achieved the completion of the shield tunnel section of the admission line.
It is reported that the entrance line shield section has a total length of 2,325 meters. Since shield starting in June, 2018, "in cooperation with the parties, the joining into in order to ensure the construction safety, quality, time limit for a project progress as the goal, give full play to the subjective initiative of nanning subway, vigorously promotes the interval excavation control, has overcome the" big slope + small curve ", wear molding tunnel, geological construction problems, and many other complex diversification, high quality finished interval excavation construction task, achieve molding tunnel "no leakage, no damage, no wrong" goal.
Related responsible person introduction, subway line 2 east extension project out of the entrance line shield section through the important role of nanning subway party building alliance. Cohesion force in the party, for leading, alliance, cooperated-builing parties through party alliance platform communication and coordination, achieved in step, unified action, design unit, command, coordinate cross the figure on time supply of rail transit construction, the nanning group coordination segment, a concerted effort to achieve the node, guarantee the track-laying construction node target task to complete.