Hangzhou metro line 8 qingpeng road station to yipengdong second road station left line shield section successfully completed

* 来源: * 作者: admin * 发表时间: 2019/11/13 10:32:57 * 浏览: 77

On November 10, with a roar, the blade plate of the shield machine slowly broke through the wall, and the shield section of the left line from qingpeng road station to yipengdong second road station of hangzhou metro line 8 appeared in front of everyone, becoming the first shield tunnel across the whole line!

The first phase of hangzhou metro line 8 is 17.1 km long, with 9 stations, including wenhai road station, qiaotou station, hezhuang station, hejing road station, qingliu road station, qingpeng road station, yipengdong second road station and xinwan road station. A new bay vehicle base.

Overcome a number of construction problems, line 8 10 shield is still in the excavation, there are two will start!

As a supporting project for the 2022 Asian games in hangzhou, the project will start from August 2018 to February 2021, and the effective construction period is only two and a half years. In order to accelerate the construction progress, a 100-day dry work was organized in the fourth quarter of last year, and a 120-day dry work was organized in September this year to accelerate the construction progress comprehensively.

Now, all there are ten of the shield are driving, and two (2) the originating, in high water-content and fine sand on a large scale in hangzhou geological construction at the same time, brings great pressure to the safety and quality management, project general contracting department establish the leadership on duty system, strengthen field management, arrange the inspector to the important link, each work area leader on duty at the scene, homework, Ben party XunZhaZu on-site inspections on a regular basis, to ensure the smooth construction smoothly.

The length of the left line of qingyi section is about 1005 meters.

In order to ensure the smooth progress of the shield machine, the project technical personnel conducted an in-depth investigation of the surrounding environment before the shield was started, and fully grasped the surrounding conditions of the river and the high-voltage tower.

After more than 90 days and nights of hard work, finally successfully completed the task! The tunneling has accumulated technical experience for the subsequent shield tunneling construction, and laid a solid foundation for the realization of the goal of fully tunneling in 2020!