2.43.6 billion! China Railway Construction Association bid Guangzhou Rail Transit

* 来源: * 作者: admin * 发表时间: 2017/10/27 10:55:00 * 浏览: 82

1, Guangzhou Rail Transit Line 18

Along the 18th line of Guangzhou Rail Transit, it passes through Nansha District, Panyu District, Haizhu District and Tianhe District. From south to North, it connects Nansha New District Wanxisha Hub, Panyu Square in Panyu District, and Pazhou District in Haizhu District. District and Zhujiang New City and Guangzhou East Railway Station in Tianhe District. Line 18 starts from Wanqingsha in Nansha District and ends at Guangzhou East Railway Station in Tianhe District. The total length of the line is 62.7 km. There are 9 stations, including 8 transfer stations, with an average station spacing of 7.8 km and a maximum station spacing of 26.0 km., for horizontal lek to Panyu Square station area; The minimum station spacing is 2.3 km, which is the section from Pomegranate Gang to Pazhou West District. There is a parking lot at the depot across the line, which is the Wanqisha Depot and the Jishou parking lot. Three main substations are set up, which are located at the Wanqisha Depot, the Jiushou parking lot, and the Chisha depot of Line 11.               

2, Guangzhou Rail Transit Line 22           

Guangzhou Rail Transit Line 22 passes through Nansha District, Panyu District and Liwan District. From south to North, it connects Nansha New District's Wanhasha Hub, Panyu Square in Panyu District, Guangzhou South Railway Station Area and Liwan District. Baiyetan area. Line 22 starts at Panyu Square and ends at Baietan in Liwan District. The total length of the line is 31km. There are 6 stations, including 4 transfer stations, reserved for Xisan and Dongsha Industrial Park stations, with an average station spacing of 6.3 km. The maximum station spacing is 7.5 km, which is from Chentougang to Xilang. The minimum station spacing is 3.5 M. It is the section from Guangzhou South Railway Station to Chentougang, and there is a parking lot for Chentougang across the board. There is a main change on the entire line, which is located in the parking lot of Chentougang.

Planned duration

Line 18 Wanqingsha to Xiancunduan, Line 22 Panyu Plaza to Chentougang: The construction period of all projects in the contract is 977 days; The construction time is tentatively scheduled for October 28, 2017; The completion time of the project is June 30, 2020.
Line 18 from the village to the Guangzhou East Railway Station section, and from Chentougang to Baiyetan section on the 22nd line: The construction period of all the projects in the contract is 1,464 days; The start time is tentatively scheduled for June 28, 2018; The completion time of the project is June 30, 2022.

Result of winning bid
First winning candidate:
(Main) China Railway Construction Co., Ltd..
China Railway Construction South China Construction Co., Ltd..
Guangdong Hydroelectric Second Bureau Co., Ltd..
Guangdong Huadun Construction Group Co., Ltd..
Bidding quotation: 43630944.39 million yuan
Project leader: Zhang Cheng
Second winning candidate:
China China Railway Co., Ltd..
Tender quotation: $43643.731.44 million
Third winning candidate:
China Transportation Construction Co., Ltd..
Tender quotation: $43741974,969