Shanghai Airport liaison line project progress

* 来源: * 作者: admin * 发表时间: 2020/07/27 10:44:30 * 浏览: 101

Current progress of airport Liaison Line Project:

Fault:

The Hu-Yu High-speed bridge: 430 bored piles, 10 pile caps and 2 piers have been completed.

No. 1 air shaft: 33 underground diaphragm walls have been completed.

No. 2 air shaft: Wall reinforcement of geosyncline is completed. Meifu Road working well: all underground diaphragm walls have been completed, and 25 dewatering Wells have been completed. Hujing Station: completed 11 underground diaphragm walls of 107.5m; 7 underground diaphragm walls of 85m were completed.

Eastern section (first construction section) :

Air shaft No.4: The site is being leveled and the temporary river filling procedure has been accepted.

Air shaft No. 5: Site formation is in progress.

Zhangjiang Station: concrete casting of heavy-duty roadways in area 1 is completed.

Air shaft no. 6: Enclosure and gate construction in progress.

Eastern section (post-construction section) : the preliminary design of the project is submitted for approval

Hongqiao Junction: preliminary design stage of the project

In addition, the main line of the airport liaison Line project (and the Vehicle base on The Lower Salt Road) is currently the project planning node:

June 30, 2023, shield section through

The track was completed on February 28, 2024

Joint test on September 30, 2024

November 30, 2024, preliminary acceptance and safety assessment

Trial operation on December 31, 2024