The "thermal slip" of the north section of the first phase of Nantong rail transit Line 1 was successful

* 来源: * 作者: admin * 发表时间: 2021/09/24 10:03:28 * 浏览: 98

After 6.5 hours of continuous efforts, at 23:30 on the evening of 17th, the first phase of rail transit Line 1 successfully completed the thermal slip test of rolling stock entrance and exit line, pingchao station to Shilifang station up and down line (including the switch area storage line), and realized the autonomous running of electric buses on the main line. The thermal slip test in the dynamic adjustment section was successfully completed, which laid a solid foundation for the commissioning of BULLET trains in the six stations and five sections of the northern section of the first phase of rail transit Line 1 from Pingchao Station to Puxian Road Station.

This hot slide section is pingdong rolling Stock line to pu10 section, passing through pingchao station, Nantong West station, Jiecun station, Hekou Station, Tangzha Park station, Puxian Road station six stations, according to the hot slide program, electric bus to the main line, storage line respectively at low speed, medium speed back and forth, the length of the hot slide section is about 22 kilometers.

Rail power supply system catenary professional since the end of the car depot hot slide, main overall catenary installation, debugging, horizontal pushing, lack of work and so on, on September 12, complete section seven stand seven interval threshold detection, catenary cold test, on September 15, complete this section catenary sending work, late on September 17, with bullet train debugging section of the thermal test. The thermal slip test proves that wheel-rail relationship and bow network relationship are normal, power supply, rail, vehicles and other equipment run well, meet the design requirements. It is reported that CRC will focus on the implementation of the first phase of the line 1 project electric communication, bullet train commissioning, comprehensive joint test and other aspects of work, comprehensively promote the construction progress, to ensure the operation in 2022.