Construction of the first cross-river tunnel of Chongqing Rail Transit Line 27 accelerated
The construction of the first cross-river tunnel in Chongqing rail transit has made new progress -- On October 12, the lower part of the middle shield of the shield machine "Yujiang No." on the left line of Chongqing Rail Transit Line 27 from Chongqing Station to Nanbin Road Station was successfully lifted into the well and the underground equipment debugging was started.
The total length of Chongqing Rail Transit Line 27 is about 49 kilometers, starting from Bishan station in the west to Chongqing East Station in the east, with 14 stations. Among them, the section between Chongqing Station and Nanbin Road Station crosses the Yangtze River in the form of a tunnel, with a total length of about 800 meters.
After the completion of Chongqing Rail Transit Line 27, it will promote the interconnection of Shapingba, Daping, Nanping, Tea Garden and other places, and provide more convenience for citizens to travel.