Wuhan metro line 16 chuan dun section right line shield tunnel started

* 来源: * 作者: admin * 发表时间: 2020/05/19 9:53:06 * 浏览: 73

At 11:8 am on 18th, with the "start to advance" command issued, wuhan metro line 16 chuan river basin station - dun mouth station section right line shield tunnel cylinder began to elongate, the blade began to rotate after touching the palm surface, for wuhan metro line 16 early completion of a solid step.

The initial chuan river pool station - dun kou station section of the right line shield section is 901 meters long, the left line shield has been launched in November last year. The first phase of wuhan rail transit line 16 starts from shamo zhoujiahe in the south and reaches guobo center in the north. The designed target speed is 120 kilometers per hour. It is a fast rail transit line connecting hannan with the main urban area.

At present, all the stations have started construction, ma ying river station, dun kou station, laoguan village depot station, laoguan village station main structure has been completed, is under construction of the subsidiary structure, the rest of the station is under construction of the main structure. The construction of the right line will fully draw on the construction experience of the left line shield, so as to ensure the safety and success of the construction and build a high-quality and high-quality project.